Timeline

Pre-Construction
Nov. 30th - Signed Contract
Dec. 13th - Flooring/Tile Selections (in our area its Rite Rug)
Dec. 17th - Final Selections Mtg
Jan. 4th - Guardian Meeting
Jan. 7th - Current house Listed for Sale
Jan. 11th - Loan Approval
Jan. 20th - Accepted Offer on current, Release Contingency
Mar. 8th - Pre-construction Meeting Scheduled

Construction
Mar 20th  - Excavate Basement
Mar. 21st - Pour Footers
Mar. 29th  - Foundation Walls Poured
Apr. 1st - Form removed from foundation
Apr. 2nd - Geo-Mat installed
Apr 2nd  4th- Wood delivered, i-beams installed, basement & garage slab poured
Apr 9th. - Framing Started
Apr. 12th  - Framing Completed
Apr. 16th - Roofing started
Apr. 15th - HVAC started
April 18th - Plumbing started
April 19th - Electrical, Guardian
Apr. 23rd - Pre-Drywall Independent Inspection
April 24th- Insulation
Apr. 25th - PreDrywall Meeting
Apr. 26th - Drywall Started
May 2nd - May 4th - Brick, Siding & Shutters
May 6th - interior goodies delivered
May 9th - Ceramic Tile

Cabinetry
- Finish Carpentry, Plumbing, Electrical
- Hardwood Flooring
- Carpeting
June 12th  13th - ESTIMATED PRE-SETTELMENT
June 14th - Closing :-) 