Thursday, April 18, 2013

Progress with a reloop

The HVAC system is in, plumbing has started and the sump pump is running. We have scheduled our inspector to come out on Tuesday and pre- drywall end of the week. I cannot tell you how excited we are to see our house come together.



The dryer vent raised per request

The furnace

Plumbing between the walls

Kids Bathroom

HVAC between family room and living room

Morning Room Patio Doors


So in addition to the progress there are a few reloops the house wrap needs to be re-done and sections of the roof as well following a rain storm with strong winds and hail. Our PM called to update us and that it will be re-done perfectly. All in all nothing too major just a few items but overall the process is going well.

I will say frequent visits is a must and helps us feel more confident in the quality of the build.



5 comments:

  1. It really is getting there. Yes, those sound like issues that are easily corrected (and may be stronger than before).

    ReplyDelete
  2. Looking good! Hopefully they get you fixed up nice and neat. The morning room doors look good!!

    Jen
    http://buildingourabode.blogspot.com/

    ReplyDelete
  3. Everythimg looks good the days are flying by!

    ReplyDelete
  4. it is looking great! Cant believe your already at drywall!

    ReplyDelete